Lecture 3 : Project Network

Note :
VISSION - WANT TO BE
MISSION - WHAT U HAVE TO DO TO ACHIEVE VISSION
OBJECTIVE - WHAT U DO TO ACHIEVE MISSION

Dalam mission da internal action and external beneficiary
  • key customer
  • contribution
  • distinction
Drawing project network
AON - Activity On Node
AOA - Activity On Arc

Critical Path Method (CPM) - bila kita dah tau exact activity duration date
PERT - bila kita xtau duration end date
Note : List 4 advantages CPM and PERT
  • Useful at many stages of project management
  • Mathematically simple
  • Give critical path and slack time
  • Provide project documentation
  • Useful in monitoring costs
Work Package

Basic Rules to follow in developing project networks
  • flow from left to right (network)
  • an activity cannot begin until all of its activities are complete
  • allow indicate precedence and flow and can cross over each other
  • identify each activity with a unique number
Lead
  • activity yg boleh berjalan serentak - Cth : Activity A dan activity leh wat serentak
  • gain more time
Lag
  • lambat - Cth : berlaku apabila activity A xsiap, activity C xleh wat