Question :
As part of a project to build a sports stadium you're managing a construct the automatic all weather roof. Level 2 of the WBS displays the phases manufacturing, electronic and controls and testing. Level 3 contains two deliverables for electronics and controls, wiring and computerization. The WBS dictionary describes the work the computerization deliverable requires as installing the management hardware and software, customizing the installation.

You are required to :
1) Construct the WBS
2) Determine the dependencies on Level 3
3) Create the WBS dictionary

Answer :
1)


2)

Install hardware must finish before install hardware can start.
Install software must finish before customize installation can start.

3)




HOMEWORK!!!

Question :
1) Construct network diagram
2) Find the critical path

Answer :
1)

2)
Path 1
Task A + Task B + Task D + Task G = 3 + 2 + 3 + 1 = 9

Path 2
Task A + Task C + Task E + Task F + Task G = 3 + 1 + 1 + 1 + 1 = 7

Path 3
Task A + Task B +Task E + Task F + Task G = 3 + 2 + 1 + 1 + 1 = 8

Path 4
Task A + Task C + Task D + Task G = 3 + 1 + 3 + 1 = 8

So as conclusion, the critical path is Path 1

Thursday, August 19, 2010

Lecture 3 : Project Network

Note :
VISSION - WANT TO BE
MISSION - WHAT U HAVE TO DO TO ACHIEVE VISSION
OBJECTIVE - WHAT U DO TO ACHIEVE MISSION

Dalam mission da internal action and external beneficiary
  • key customer
  • contribution
  • distinction
Drawing project network
AON - Activity On Node
AOA - Activity On Arc

Critical Path Method (CPM) - bila kita dah tau exact activity duration date
PERT - bila kita xtau duration end date
Note : List 4 advantages CPM and PERT
  • Useful at many stages of project management
  • Mathematically simple
  • Give critical path and slack time
  • Provide project documentation
  • Useful in monitoring costs
Work Package

Basic Rules to follow in developing project networks
  • flow from left to right (network)
  • an activity cannot begin until all of its activities are complete
  • allow indicate precedence and flow and can cross over each other
  • identify each activity with a unique number
Lead
  • activity yg boleh berjalan serentak - Cth : Activity A dan activity leh wat serentak
  • gain more time
Lag
  • lambat - Cth : berlaku apabila activity A xsiap, activity C xleh wat

Lecture 2 : Project Life Cycle

Project Life Cycle

Figure 1: Project Life Cycle - Four Basic Phases

Untuk senang paham =)
Initiating
  • project feasibility - boleh dijanjikan @ x, kira kena wat study (kaji)
  • project charter (product yg kuar) - role n responsibility of team member, project scope (triple constraint), output n deliverable (slh satu terhasil or both), project structure

Planning
  • cth : deliverable - 10 buah rumah dihasilkan dan 2 kandang kambing
  • start plan keje - Work Breakdown Structure (WBS), Gantt Chart, others
WBS

Gannt Chart
Project Gantt Chart

Executing/Controlling
  • Task List
  • Issue List
  • Bug List (kalu wat system)
  • Deliverables
Closing
  • compile suma

Example - kalu wat system, model untuk develop system
  • PLANNING
  • ANALYSIS
  • DEVELOPMENT
  • IMPLEMENT