Drawing project network
AON - Activity On Node
AOA - Activity On Arc
Critical Path Method (CPM) - bila kita dah tau exact activity duration date
PERT - bila kita xtau duration end date
Note : List 4 advantages CPM and PERT
- Useful at many stages of project management
- Mathematically simple
- Give critical path and slack time
- Provide project documentation
- Useful in monitoring costs
Work Package
Basic Rules to follow in developing project networks
- flow from left to right (network)
- an activity cannot begin until all of its activities are complete
- allow indicate precedence and flow and can cross over each other
- identify each activity with a unique number
Lead
- activity yg boleh berjalan serentak - Cth : Activity A dan activity leh wat serentak
- gain more time
Lag
- lambat - Cth : berlaku apabila activity A xsiap, activity C xleh wat