2)
Path 1
Task A + Task B + Task D + Task G = 3 + 2 + 3 + 1 = 9
Path 2
Task A + Task C + Task E + Task F + Task G = 3 + 1 + 1 + 1 + 1 = 7
Path 3
Task A + Task B +Task E + Task F + Task G = 3 + 2 + 1 + 1 + 1 = 8
Path 4
Task A + Task C + Task D + Task G = 3 + 1 + 3 + 1 = 8
So as conclusion, the critical path is Path 1